As part of the task, PORR is responsible for the construction of a 5.5-meter-wide asphalt road, the construction of a 2-meter-wide sidewalk with individual entrances, as well as the construction of lighting and drainage. During the course of the work, the contractor will remove existing collisions with power, gas and teletechnical networks.
Facts and figures at a glance:
Project type: | Construction of Celulozy Street in the Wawer district of the city of Warsaw |
Scope of works: | Build |
Client: | The Wawer District Office of the City of Warsaw |
Contractor: | PORR S.A. |
Contract value: | PLN 5.221 million |
Time for execution: | November 2024 |