The renovation will not only refresh the look of the stops but will increase their accessibility and convenience for passengers. Apart from the platforms renovation, the broad scope of works encompasses rebuilding the adjacent tracks with the overhead traction network. The key part of both investment tasks will be the reconstruction of the double-edge platforms and the construction of lift shafts with cranes. In terms of tracks, the replacement of rails and the ballast replenishment will be carried out. Additionally, the support structures and suspensions of the traction network will be renewed.
As a part of the modernisation of the Gdańsk Stocznia stop, the platform will be equipped with a new shelter while two existing ones will undergo maintenance. At the Gdynia Stocznia - Uniwersytet Morski stop, the existing platform canopies will be replaced by two new full-size platform shelters. Both stops will also be equipped with small architecture elements.
- We are pleased to have been entrusted with the realisation of these two modernisations, said Siegfried Weindok, Member of the Management Board of PORR S.A. - What is important, these are not only our first two railway investments in the Tricity, but also our first contract signed with The Fast Urban Railways as an investor. We hope this is the beginning of a successful cooperation, which will allow us to demonstrate our expertise and high standards in terms of execution.
According to the plan, the two tasks will be executed within 24 months. The project documentation, including obtaining a building permit decision, is to be ready within 10 months. The modernisation is expected to deliver a new quality of infrastructure that will encourage passengers to choose an environmentally friendly mode of transport such as rail.
Facts and figures at a glance
Project type: | Modernisation of two Fast Urban Railway passenger stops in Tricity: Gdańsk Stocznia and Gdynia Stocznia – Uniwersytet Morski |
Scope of works: | Design & Build |
Client: | The Fast Urban Railway – Polish State Railways in Tricity |
Contractor: | PORR S.A. |
Contract value: | PLN 21 m net |
Time for execution: | 24 months |