Aktualny Zakres akredytacji wyd. 7 z dn. 19.06.2023
Zakres akredytacji Nr AB 1689 PCA Scope of accreditation No. AB 1689 ZAKRES AKREDYTACJI LABORATORIUM BADAWCZEGO SCOPE OF ACCREDITATION FOR…
-
Wawer Celulozy ENG Wawer Celulozy ENG
Press release PORR contractor for road in Warsaw's Wawer district Warsaw, 27.02.2024 - The Wawer District Office of the City of Warsaw has signed a contract…
-
ITPOE Gorlice ENG ITPOE Gorlice ENG
Press release PORR will build a modern installation for thermal processing plant in Gorlice Warsaw, 27.02.2024 – PORR S.A. will build a modern installation for…
-
Warsaw, March 21, 2024 - PORR S.A. has signed a contract with the Port of Gdańsk for the modernization of Rudowe and Bytomskie Quays. The total length of the quays to be reconstructed is over 450…
-
BER12 Data Center
In Ludwigsfelde near Belin, PORR is in charge of the construction of a database known as BER12.
The contract between PORR and Vantage Data Centers, one of the world’s largest…
-
PSE S.A. Data Center
The project will involve the construction of an office and administration building with a total area of approximately 26,000 sqm and a volume of about 158,000 cubic metres.
The…
-
Qubes – Technologie Campus
The Munich Technology Campus (known in German as Technologie Campus München, or TCM) is home to the City of Munich’s entire IT department and two catering providers. In…
-
WAW 11.1 Data Center
Under a Design & Build contract, PORR built a two-storey building in Warsaw with a total area of 6,730 sqm and a capacity of 8 MW. The facility encompasses two server spaces,…
-
DC01 Data Center
The construction was completed between February 2022 and March 2023. In just over a year, in the town of Jawczyce, we built a modern two-storey building with extensive technological…